Construction Update

We're almost in the clear! I'll continue to call/text the day of your appointment if things are looking especially crazy, but here's an update straight from a Randolph Township email, in regards to the ongoing construction:

"Announcement: Sussex Turnpike Construction - Traffic Impact
The Morris County Department of Planning and Public Works anticipates roadwork impacting traffic flow to be finished by early October. The updated schedule provided by the County is:
September 1-16: Optimum and Verizon completion of pole and wiring relocation
September 12–23: General Contractor completion of remaining curb and sidewalk installation
September 26–October 14: General Contractor completion of road resurfacing and line striping
October–December: General Contractor completion of landscaping, off road improvements, and punch list work.
The ongoing construction activities combined with the reopening of school and normal commuting patterns will likely cause increased congestion in the Mount Freedom area of Sussex Turnpike during the morning and evening rush hours through early October."